17 November, 2014 |
Dear Resident,
Following the recent communications with the Community and to keep you posted about our Community Services, please find below the following updates:
|
COMMUNITY FACILITIES/SERVICES |
UPDATE |
1 |
Way-finding signage |
6 months from Date |
2 |
Security Gatehouses |
It is currently on hold with RTA. Once approved, they should be operational within 6-8 weeks. |
3 |
Landscaping rectifications |
2-3 months |
4 |
Road Link between Jumeirah Village Triangle and Jumeirah Park: |
End of November/Beginning of December 2014. |
5 |
Performance of Security Service Provider |
We are planning to replace Al-Jaber. |
6 |
Street lighting in District-1 and Park |
DEWA to energize in 2 months |
7 |
Groundwater Pond |
We are engaging a consultant to analyse the Groundwater status in the whole Community and design solutions for the long term. |
|